PCSB SK- GAS

  • Project Title: Provision of Pre-Commissioning, Commissioning and De-Commissioning of Pipeline and Associated for Petronas Carigali Sdn. Bhd.
  • Client: PCSB-SKG
  • Description: Chartering-AHTS DP1-Accomodation
  • Project Duration: 90 days
  • Duration of Work Orders: 2 months (FIRM) + 31 days + 53 days + 55 days (EXTENSION)
  • Project Title: Provision of Vessel Support Duties, Accommodation, Storage, Transportation Equipment, for F9 Offline Intelligent Pigging Campaign
  • Client: PCSB-SKG
  • Description: Chartering-AHTS-Support Duties, Accommodation, Storage & Transportation Equipment
  • Project Duration: 30 days
  • Duration of Work Orders: 30 days (FIRM)
  • Project Title: Provision of Shutdown Maintenance Project Team for Intelligent Pigging, Pipeline and Riser Maintenance Works.
  • Client: PCSB-SKG
  • Description: Chartering Accommodation for 80 pax
  • Project Duration: 30 days
  • Duration of Work Orders: 21 days (FIRM) + 7 Days (EXTENSION)
  • Project Title: Provision of FCB to Support F9JT-A Pipeline Maintenance Campaign
  • Client: PCSB-SKG
  • Description: Chartering-FCB
  • Project Duration: 30 days
  • Duration of Work Orders: 7 days (FIRM) + 11 days (EXTENSION)